Skip to content

I do not know whether my self-build is pre-build or live

A project can cross the commitment boundary before the main building work starts.

Updated: 13 September 2026. By Jack Butler-Kettle, Quantity Surveyor & Claims Consultant.

01The month happens
02The report assembled
03The numbers read
04The forecast ahead
05The job's end
You are here: The next financial review depends on what has been committed.

What's happening?

Land, design, planning, surveys and investigations alone remain pre-build, even when they have cost money. An accepted building, trade, package or material order, a kit or build deposit, substantive enabling work or substantive building work makes the project live. A paused or partially procured project remains live. Choosing the wrong route can hide commitments before the main build or treat a live cost position as an uncommitted proposal.

The solution

If a self-build budget is under pressure, separate missing scope, paid, owed, committed and unpriced costs, reserve and dated funding. Distinguish total affordability from a timing shortfall, then list the immediate evidence and decisions needed.

Select Pre-build or Live Build from the actual construction commitment boundary, not a project stage label, and preserve both service paths. The review identifies actions and owners; it does not promise resilience, funding or a programme outcome.

Example

The situation

A household building a £420,000 house has bought the plot, paid the architect and the structural engineer, been granted planning and paid a £15,000 deposit to a timber frame company. Nobody has dug anything, so the household thinks it is still pre-build.

What happens

  1. The deposit is an accepted order for the frame, so the project is live and the Live Build review is the right one.
  2. The money is separated into piles: £58,000 paid in fees, surveys and the deposit; £4,000 owed to the engineer; the £128,000 balance of the frame contract committed on its stage dates.
  3. The kitchen, the landscaping and the driveway are unpriced, around £38,000 on the architect's estimates; the electricity connection is missing altogether, never carried in the budget and quoted at £9,000; there is no reserve.
  4. The mortgage draws in stages, and the frame's second payment falls three weeks before the stage that follows the foundations.
  5. The forecast total comes to £441,000 against £455,000 of funds, so the house is affordable; the problem is a timing shortfall of £22,000 for three weeks, a different problem with a different fix.
  6. The frame company agrees to move the payment to the stage date, the connection goes into the budget, and a small reserve is set from the balance.

The budget in piles

PileAmount
Paid: fees, surveys and the deposit£58,000
Owed to the engineer£4,000
Committed: balance of the frame contract£128,000
Unpriced: kitchen, landscaping and driveway£38,000
Missing: electricity connection£9,000
Forecast total£441,000

The outcome

The house is affordable at £441,000 against £455,000 of funds; the £22,000 timing shortfall is closed by moving the frame payment, and each action has a name and a date beside it.

Related answers