Live Build Stress Test

Risk mitigationFixed FeeFor Self BuildersTimetable agreed in writing at scoping

The Live Build Stress Test reconciles paid money, commitments, unpaid liabilities, changes, remaining work, cost to complete, reserve and dated shortfalls at an agreed evidence date. It shows the live financial position after procurement or work has begun, including a paused or partially procured project.

The problem

Once a building, trade, package or material order is accepted, a kit or build deposit is paid, or substantive enabling or building work starts, the project is live even if the main building has not begun. A paused build and a partially procured project stay live. Paid costs alone cannot show what remains: commitments, unpaid liabilities, changes, unpriced work, cost to complete, reserve and the dates money is needed all have to be reconciled.

The solution

At an agreed evidence date we reconcile the live position and separate what has been paid, committed, owed, changed, still to be done and not yet priced. We model cost to complete, remaining reserve and dated shortfalls, explain the risks and set out decisions and necessary actions with owners. This is a financial review, not a cost-plan preparation, programme assurance, design, survey, legal, tax or financial-product service.

How it works

  1. You describe what has been procured and what remains

    We use the project call to establish the live commitment, paused or active status, remaining scope and decision the review must support.

  2. You provide the available live evidence

    You send the project and financial evidence that exists, including gaps. The final information requirement is agreed after the call and is not assumed from a generic list.

    • A

      Project location, build route, finished scope, next decision and evidence date and the first construction commitment or works and current build status

      Essential

      Without it: A whole-project comparison has no reliable scope

      Where to find it: Your project notes and initial discussion

      Why we need it: Set a common project scope and decision

    • B

      Original budget and current forecast, accepted prices, remaining-work estimates, exclusions and every available revision

      Essential

      Without it: The expected completion cost cannot be assessed reliably

      Where to find it: Your budget file, designer, builder and suppliers

      Why we need it: Establish a traceable baseline and identify missing work

    • C

      Paid costs, unpaid invoices, accepted orders, deposits, retentions, existing commitments and actual work completed, with any disputed or uncertain liabilities

      Essential

      Without it: Costs, liabilities or available cash could be misstated

      Where to find it: Statements, invoices, quotations, orders and correspondence

      Why we need it: Separate paid history, unpaid obligations and remaining work

    • D

      Cash held for the project, undrawn funds, offers and release conditions, repayments and expected receipts

      Essential

      Without it: No reliable funding or cash conclusion can be given

      Where to find it: Relevant statements, funding offers and your adviser

      Why we need it: Establish available money and its conditions

    • E

      Actual progress and remaining-work dates supplied by the responsible team, payment and retention dates, overdue sums and funding-release conditions

      Essential

      Without it: A total-cost comparison cannot prove payments can be met

      Where to find it: Builder, designer, suppliers, lender and your records

      Why we need it: Establish when payments are due and funding becomes accessible

    • F

      Current drawings, specification, scope descriptions and undecided selections

      Important

      Without it: Completeness and specification exposure remain uncertain

      Where to find it: Your designer and supplier information

      Why we need it: Compare prices against the intended finished scope

    • G

      Ground, drainage, utilities, access, levels, flood and other site or specialist evidence held

      Important

      Without it: Uninvestigated site exposure cannot be treated as resolved

      Where to find it: Surveys, design team, utility providers and site records

      Why we need it: Identify abnormal cost evidence and unresolved questions

    • H

      Executed or accepted builder, trade and supplier documents, payment and deposit terms, price-change terms and remaining unprocured packages

      Important

      Without it: The commercial exposure may be misunderstood

      Where to find it: Quotations, contracts, orders and correspondence

      Why we need it: Check scope gaps, pricing exposure and payment protection

    • I

      Household reserve to protect, project allocation, accommodation costs and proposed own labour or unpaid help

      Essential

      Without it: The model could spend money that cannot be released

      Where to find it: Your agreed household allocation and cost evidence

      Why we need it: Separate project funds from household resilience

    • J

      Agreed and proposed changes, current concerns, setbacks, unfinished work, paused-work costs and mitigation already arranged

      Essential

      Without it: Known exposure could be omitted from the tests

      Where to find it: Your discussion notes and project correspondence

      Why we need it: Select project-specific scenarios without double counting

    • K

      Previous cost reviews, advice and scenario models where available

      Optional

      Without it: No comparison with previous advice can be made

      Where to find it: Earlier advisers and your project files

      Why we need it: Explain changed assumptions and unresolved earlier findings

    Copies are fine. Send what you have and we will tell you what's missing.

  3. We confirm the live boundary and evidence date

    We record the evidence cut-off and the qualifying commitment or work that makes the project live. A paused or partly procured project remains in this route.

    Live position recorded

    The review does not revert to pre-build because work has paused, the main building has not started or only part of the project has been procured.

  4. We reconcile money and commitments

    We separate paid money, unpaid liabilities, accepted commitments, changes and remaining work, so a low paid-cost figure cannot hide what is already owed or ordered.

  5. We calculate cost to complete and reserve

    We test the remaining scope, cost to complete, reserve and dated access to funding against the evidence and assumptions at the cut-off.

  6. We model the shortfalls and risks

    The workings and scenario model show the assumptions used, the risks exposed and any dated shortfall. It does not predict black swans or assure that a programme can be achieved.

  7. We report the findings and discuss the decisions

    The report states what was reviewed, what was found, what it means, the necessary actions with owners and decision points, and how Jack can help further. We discuss the findings with you.

We hand back the live financial position

See the full outcome in What you get.

What you get

A written review with checked workings, a scenario model and an explained risk profile. The profile considers budget completeness; design and specification; ground, site and access; materials and supply chain; contractors and procurement; labour and work you plan to do yourself; duration and weather costs; funding and cashflow; approvals, tax and completion requirements; and household reserves and contingency. The review assesses their financial effects from the information available and identifies any specialist evidence still needed. Where the information supports an assessment, we explain each material issue’s severity on a 1–5 scale and show the strength of its evidence separately. The overall assessment reflects the highest material unresolved severity, rather than an average. If essential information is missing, we mark the relevant assessment as not assessable and keep any demonstrated critical finding visible. The score helps you prioritise action; it is not a percentage chance of success or failure. The report answers five practical questions: what did we review, what did we find, what does it mean for you, what should happen next, and how can we help if further work is worthwhile? Actions have an owner and a decision point, including steps you or your current team can take. Any optional further service is separately scoped and is not needed to make the report useful.

The Handover Pack accompanies the work with its dates and sources, likely outcomes and responses, scope boundaries and ready-to-send correspondence where needed.

A one-off Fixed Fee and delivery date are agreed in writing after the project call, evidence review and scope are established.

We will agree the timetable in writing when we scope the work. We will confirm the start and target dates once we have the information needed for the agreed work. If something is missing or unusable, we will explain the options and agree any change before starting. We will confirm your target date.

Where the turnaround is stated in working days, the confirmed start day is day zero.

The turnaround ends when we issue the agreed deliverable and its supporting handover documents.

Tell us about any live deadline straight away. Contractual or statutory deadlines continue to run while information is being gathered.

We will confirm the target date for your agreed work.

Free Service Pack

A step-by-step Handbook, with the templates and working documents you need to carry out the work it covers yourself. You supply your own project information and records.

Follow the Handbook's scope and stopping points, and obtain independent advice where required. The pack is not project-specific advice or independent sign-off.

This review is separate from work that checks a payment or prices a change. Where the findings need a repeating control, Valuation & Payment Checking or Variation Control can be separately scoped. If the whole money side needs a continuing owner, Commercial Management is another separately scoped option. The checked method-specific workbook is listed separately as the Live Build Stress Test Model. None is required to understand this report.