Skip to content

How does NEC4 clause 51 work?

The Project Manager certifies a payment within one week of each assessment date, the certified payment is made within three weeks of the assessment date or the period stated in the Contract Data, and interest is paid on late payments and on amounts later corrected.

Updated: 15 September 2026. By Jack Butler-Kettle, Quantity Surveyor & Claims Consultant.

The answer

Clause 51 turns the clause 50 assessment into a certificate and a payment, and every period in it runs from the assessment date, not from the certificate. Under clause 51.1 the Project Manager certifies a payment within one week of each assessment date. The first payment is the amount due; each later certified payment is the change in the amount due since the last certificate, so a certificate can be for a payment from the Contractor to the Client where the amount due has fallen. Under clause 51.2 each certified payment is made within three weeks of the assessment date, or within a different period if one is stated in the Contract Data, and if a payment is late interest is paid on the late amount from the date it should have been made until the date it is. Under clause 51.3, where an amount due is corrected in a later certificate, whether because of a mistake, a compensation event or a decision in dispute resolution, interest is paid on the correcting amount from the date the incorrect amount was certified until the date the correction is certified. The interest rate and its calculation are in the contract and are not repeated here. Where the contract includes Option Y(UK)2 the due date, the final date for payment and the payment notices under the Construction Act sit on top of this clause, and that page explains them. What goes wrong: Contractors and Clients count the three weeks from the certificate, which shortens or lengthens the period by however late the certificate was; a certificate that arrives late is treated as postponing payment, when the payment date has not moved; corrections are certified without the interest clause 51.3 attaches to them; and Contract Data periods that differ from three weeks are missed because nobody read the entry. Read the certificate against the assessment date every time.

Example

The situation

The assessment date falls on a Monday and the Contract Data entry leaves the payment period at three weeks. The Project Manager certifies within one week, on the following Friday, an amount due of £272,000 against a previous amount due of £200,000.

What happens

  1. The certified payment is £72,000, the difference between the two amounts due.
  2. Payment is due within three weeks of the Monday assessment date, not of the Friday certificate.
  3. Where the Client pays a week late, interest runs on £72,000 for that week at the contract's rate.
  4. Where the Project Manager later finds the certificate under-certified by £10,000 through a mistake, it is corrected in a later certificate.
  5. Interest is paid on the £10,000 from the date of the incorrect certificate to the date of the correcting one.

The certificate in figures

ItemAmount
Amount due certified£272,000
Previous amount due£200,000
Certified payment£72,000
Later correction for under-certification£10,000

The outcome

The three-week payment period runs from the assessment date, and interest follows both a late payment and a corrected under-certification.

The free Payment Calendar & Tracker counts the certificate and payment periods from the assessment date, where the clause starts them.