Apply against the pricing document, not last month plus a bit
The application that gets cut is the one that grew by a rounded percentage. Measure progress against the bills or activity schedule line by line, and let the total be whatever the lines add up to. An assessor argues with an estimate; a measured line with a marked-up drawing behind it must be engaged on the merits.