Skip to content

What is the notified sum?

The sum stated in whichever notice operates for that payment cycle: the Payment Notice, or the application in its place if no Payment Notice was given.

Updated: 15 September 2026. By Jack Butler-Kettle, Quantity Surveyor & Claims Consultant.

The answer

The notified sum is the amount that the operative notice for a payment cycle says is due. Where the payer gives a valid Payment Notice in time, that notice fixes it. Where the payer gives none and the contract makes the payee's application a default notice, the application fixes it. Under section 111 of the Construction Act the payer must pay the notified sum on or before the final date for payment unless a valid Pay Less Notice, served in time, states a lower sum, in which case that lower sum is what must be paid. The notified sum is not a valuation of the work; it is a figure produced by the notice machinery, which is why a payer who misses both notices can owe the full application whatever the work was worth, and why the true value is a separate question resolved separately.

Example

The situation

An application of £96,000 goes in on the contract's date. The contract allows five days for a Payment Notice and sets a final date for payment, before which any Pay Less Notice must arrive.

What happens

  1. The application for £96,000 is issued on the contract's date.
  2. No Payment Notice arrives within the five days the contract allows.
  3. No Pay Less Notice arrives before the final date for payment.

The outcome

The notified sum is £96,000 and it is payable in full on the final date for payment. Whether £96,000 was the right value of the work is a different dispute and does not change what fell due that month.

The Notified Sum Audit reads every past cycle for sums that fell due and were never paid.