How does the JCT final account work?
The Contractor sends its documents within six months of practical completion, the statement of adjustments to the Contract Sum follows, and the Final Certificate closes the account with conclusive effect under clause 1.9 unless proceedings are started in time.
Updated: 15 September 2026. By Jack Butler-Kettle, Quantity Surveyor & Claims Consultant.
The answer
The JCT final account under SBC/Q 2016 is the final adjustment of the Contract Sum, done through the final adjustment and Final Certificate provisions in section 4, and it ends in a Final Certificate that under clause 1.9 becomes conclusive on the matters it lists unless proceedings are started in time. The sequence is fixed. Not later than six months after practical completion the Contractor sends the Architect/Contract Administrator, or the Quantity Surveyor if so instructed, all the documents necessary for adjusting the Contract Sum: the Variation account, daywork sheets, loss and expense records and the rest. The Quantity Surveyor then prepares, and the Architect/Contract Administrator sends the Contractor, the statement of all the adjustments to the Contract Sum, together with the ascertainment of any loss and expense, within the period the clause states. The Final Certificate is issued within two months of the latest of three events: the end of the Rectification Period, the date of the Certificate of Making Good, and the date the statement of adjustments and ascertainment were sent to the Contractor. It states the adjusted Contract Sum, the total already certified, and the balance due either way. Clause 1.9 then makes the certificate conclusive evidence of the matters it names, including that all necessary adjustments to the Contract Sum have been made and that the loss and expense paid is in final settlement, save where proceedings have been started within the period the clause gives. Under the Design and Build Contract 2016 the same job is done by the Contractor's Final Statement, or the Employer's Final Statement where the Contractor does not produce one, with a similar conclusive effect. What goes wrong is sending the documents late and losing the Contractor's grip on the timetable, a statement of adjustments that was never checked line by line against the Contractor's account, and a Final Certificate that lands while the parties are still arguing.
Example
The situation
The Contract Sum is £3,000,000 and practical completion has been certified. Within six months the Contractor sends its final account documents showing £3,260,000: Variations of £210,000, ascertained loss and expense of £40,000 and fluctuations of £10,000.
What happens
- The Quantity Surveyor's statement of adjustments, sent within the period the contract allows, puts the Variations at £185,000 and the loss and expense at £32,000, so the adjusted Contract Sum is £3,227,000.
- The Rectification Period ends and the Certificate of Making Good is issued.
- The Final Certificate follows within two months of the latest of those and the statement, stating the adjusted sum, the amount certified to date and the balance due.
- If the Contractor disputes the £25,000 of Variations struck out, it must start proceedings within the period clause 1.9 gives or the certificate becomes conclusive on that figure.
The account in figures
| Item | Contractor's documents | Statement of adjustments |
|---|---|---|
| Contract Sum | £3,000,000 | £3,000,000 |
| Variations | £210,000 | £185,000 |
| Loss and expense | £40,000 | £32,000 |
| Fluctuations | £10,000 | £10,000 |
| Adjusted Contract Sum | £3,260,000 | £3,227,000 |
The outcome
The Final Certificate states £3,227,000, the £3,150,000 certified to date, and £77,000 as the balance due to the Contractor.
